Thursday 25 October 2012

Production Performance of Oil & Natural Gas sector for the month of September, 2012

Production Performance of Oil & Natural Gas sector for the month of September, 2012
I.        
A. CRUDE OIL PRODUCTION  – PERFORMANCE

Month / Period
Planned Target (TMT)
Actual Production (TMT)
%age achievement
Surplus(+) Shortfall(-) Vis-à-vis target (%age)
Surplus(+) Shortfall(-) over last year   (%age)



September, 2012*
3252.355
3066.549
94.3
-5.7
-1.7

April-September, 2012*
19758.530
19084.016
96.6
-3.4
-0.8

April-September, 2011

19229.089




TMT: Million Metric Tonnes.



*: Provisional.

B. COMPANY-WISE ACHIEVEMENT




Company / State
Planned Target (TMT)
Actual Production (TMT)
%age achievement
Surplus(+) Shortfall(-) (%age)

ONGC
1937.400
1810.000
93.4
-6.6

  Gujarat
440.000
418.000
95.0


  Andhra Pradesh
22.000
23.000
104.5


  Tamil Nadu
17.000
21.000
123.5


  Assam
98.000
102.000
104.1


  Tripura
0.4000
2.0000
500.0


  Mumbai Region   (incl Mumbai High)
1360.000
1244.000
91.5


OIL
324.300
305.029
94.1
-5.9

  Assam
322.300
303.237
94.1


  Arunachal Pradesh
2.000
1.792
89.6


PRIVATE/JVC
990.655
951.520
96.0
-4.0

TOTAL
3252.355
3066.549
94.3
-5.7

C. REASONS FOR SHORTFALL

Company / State
Reasons for shortfall

ONGC (Gujarat)
Poor Influx, increasing water cut trend & Power shutdown.

ONGC (Mumbai High Offshore)
Less than anticipated oil gain from development wells, side track, new & workover wells. Production affected due to less than anticipated oil gain from Vasai East. Delay in project execution of G-I field. 

OIL (Assam & Arunachal Pradesh)
Several OIL Bandhs/Blockades by various  Groups  during the month of September, 2012 and frequent miscreants activities in the fields.

Pvt./JVCs  ( Rajasthan)
Less than estimated oil production from Bhagyam field.

Pvt./JVCs  ( Arunachal Pradesh)
Only producing well Amguri # 14 ceased to flow since October, 2011 due to sand ingress in wellbore.

Pvt./JVCs ( Western Offshore-Panna-Mukta)
Lower oil production due to delay in well intervation jobs,  and underperformance of MA # 4 & # 8 wells.  NANG production is less due to almost no flow from PG#1 &# 10 wells.

A statement showing Crude Oil Production during September, 2012 and cumulatively for the period April- September, 2012 vis-à-vis 2011-12 planned production is at Annexure-I.







II.  A. REFINERY PRODUCTION

    (IN TERMS OF CRUDE THROUGHPUT)

Month / Period
Planned Target (MMT)
Actual Production (MMT)
%age achievement
Surplus(+) Shortfall(-) Vis-à-vis target         (in %age)
Surplus(+) Shortfall(-) over last year          (in %age)

September, 2012*
14.225
14.129
99.3
-0.7
11.4

April- September, 2012*
87.041
88.178
101.3
1.3
5.4

April- September, 2011

83.649




*: Provisional.
















The crude throughput in IOC (Barauni, Mathura & Panipat), BPCL (Mumbai & Kochi ), HPCL (Mumbai), MRPL (Mangalore), RIL (Jamnagar) & Essar Oil Ltd. Vadinar refineries have exceeded their planned target.

The crude throughput in  IOC (Guwahati, Koyali, Haldia, Digboi  & Bongaigaon), BORL (Bina), HPCL (Visakh), CPCL (Manali & Narimanam), NRL (Numaligarh) & ONGC Tatipaka  refineries was less than their planned target.

B. REASONS FOR SHORTFALL :



Company / State
Reasons for shortfall

IOC (Haldia)
Throughput is restricted due to Breech Lock Exchanger problem in Hydro Cracker unit.

IOC (Guwahati)
Throughput lower due to extended planned shutdown for Coker revamp.

IOC (Koyali)
Throughput is restricted due to high inventry of Raw Petroleum Coke and Black Oil.

IOC (Bongaigaon)
Throughput lower due to power plant outage.

HPCL, Visakh
Throughput lower than the MOU excellent Target due to deferment of planned CDU-III shutdown.

BORL, Bina
On three occassions there was a state grid power failure affecting power supply to the units, resulting in reduction in Crude Throughput.  Refinery was under shutdown from 31st August 2012 to 25th September 2012 for maintenance works in Hydrogen unit & Refinery flare system.

A statement showing refinery-wise production during the month of September, 2012 and cumulatively for the period April- September, 2012 vis-à-vis 2011-12 planned target is at Annexure-II.


III.  REFINERY CAPACITY UTILISATION [excluding RPL(SEZ)]

Month
Utilisation (%)
Period
Utilisation (%)

 September, 2012*
97.1
April- September, 2012
99.3

 September, 2011
96.5
April- September, 2011
104.3



The refinery-wise details of the capacity utilisation during September, 2012 and cumulatively for the period April- September, 2012 vis-a-vis 2011-12 are given in Annexure-III.







IV.        A.  NATURAL GAS PRODUCTION



Month / Period
Planned Target (MCM)
Actual Production (MCM)
%age achieve-ment
Surplus(+) Shortfall(-) Vis-à-vis target    (%age)
Surplus(+) Shortfall(-) over last year     (%age)

September, 2012*
3393.969
3362.764
99.1
-0.9
-14.8

April- September, 2012*
20534.006
21353.025
104.0
4.0
-12.5

April- September, 2011

24406.602




MCM: Million Cubic Metres.         



*: Provisional.

B.     COMPANY-WISE ACHIEVEMENT



Company / State
Planned Target (MCM)
Actual Production (MCM)
%age achievement
Surplus(+) Shortfall(-) (%age)

ONGC
1941.134
1924.277
99.1
-0.9

  Gujarat
104.444
150.320
143.9


  Rajasthan
1.219
1.379
113.1


  Andhra Pradesh
83.239
98.107
117.9


  Tamil Nadu
111.230
99.851
89.8


  Assam
37.381
41.815
111.9


  Tripura
84.553
48.169
57.0


  Mumbai High Offshore
1519.068
1484.636
97.7


OIL
254.000
225.229
88.7
-11.3

  Assam
232.000
204.600
88.2


  Arunachal Pradesh
1.600
1.762
110.1


  Rajasthan
20.400
18.867
92.5


PRIVATE/JVC
1198.835
1213.258
101.2
1.2

  Onshore $
11.099
64.166
578.1


  Offshore
1187.736
1149.092
96.7


TOTAL
3393.969
3362.764
99.1
-0.9

$: Including Coal Bed Methane production.



C.     REASONS FOR SHORTFALL

Company / State
Reasons for shortfall

ONGC (Tripura)
Less offtake by  consumers.

ONGC (Offshore)
Delay in Project execution of G-1 field.

OIL (Assam )
Less drawal by BVFCL and LTPS and less than desired production potential.

Pvt./JVCs ( KG-DWN-98/3)
Oil/ Gas production is much less in D1,D3 & MA fields Vis-à-vis FDP approved rates.  Total 6 wells in D1d,D3 & 2 wells in MA have ceased to flow due to water/sand ingress.

A statement showing natural gas production during September, 2012  and cumulatively for the period April- September, 2012 vis-à-vis 2011-12 is at Annexure-IV.

No comments:

Post a Comment