MINUTES FOR 32ndEXPERT APPRAISAL COMMITTEE
(INDUSTRY-2) HELD DURING16th?17thFebruary, 2012
VENUE: Scope
Complex, Core 6, 5th Floor, IOCL Conference Room, Ministry of
Petroleum and Natural Gas, Lodhi Road, New Delhi 110 003.
TIME 10.00 A.M.
32.0 Opening Remarks of the Chairman
32.1 Confirmation of
the Minutes of the 31stMeeting of the Expert Appraisal Committee
(Industry-2) held during 12th?13thJanuary, 2012.
32.3
Reconsideration:
32.3.1.
Expansion of Ammonia (2200 MTPD) and Urea (3860 MTPD) by installing Urea Plant
(1.27 MTPY Phase-III) based on Natural Gas at Kakinada, District East Godavari,
Andhra Pradesh by M/s Nagarjuna Fertilizers and Chemicals Ltd. (EC)
The project proposal was considered in the 29th
EAC meeting held during 17th -18th November, 2011 wherein
the committee desired following additional information and matter was deferred
till the desired information is submitted:
Value of CO and HC should be
re-checked. Stack emission of NOx may be given in mg/Nm3 instead of
emission rate.
Rechecking of distance of ground
level concentration for SO2 and NOx, which is mentioned
as 14.1 km in the EIA report. Action plan for water conservation to reduce
water consumption. Water consumption should match the existing plant and should
not exceed the existing requirement for production of fertilizer/MT. Wastewater
generation should also be reduced accordingly.
Effluent characteristics are
given only for 4-5 parameters. Other parameters as per CPCB guidelines should
also be monitored and submitted.
Table 3.4 should be rechecked
where raw water inlet and effluent outlet is mentioned.
Action plan for solid and
hazardous waste management and disposal should be given.
Justification for additional NH3
storage facilities.
Hazardous waste disposal scheme
for all the hazardous wastes to be disposed off should be submitted.
Keeping in view of Tsunami, Risk
assessment should also include action plan. All coastal area facilities have to
be included in action plan.
Revised Quantitative Risk
Assessment considering worst case Scenario determining frequency of occurrence
of Scenarios and consequence thereof.
Provide the Fertilizer Complex`s
"List of Near Misses" for last two Calendar years.
In Public Hearing Report, it is
mentioned that there is no storage of NH3 but, in actual, there is
storage of NH3. Clarification may be submitted.
TOR letter and its compliance,
Public Hearing and point-wise clarification alongwith commitments made with
public should be included in the EIA/EMP report.
Project proponent vide letter
dated 27th December, 2011 submitted the following information:
1. Project
proponent has informed that figures uder the columns of CH4 and N-CH4
had got inadvertently reversed in the original environmental impact assessment
report. The NOx values have been given in mg/NM3 as advised.
2. The ground
level concentrations for SO2 and NOx have been re-checked
and found to be correct. It may kindly be noted that under stable and low wind
conditions from the stacks with small heights, there is possibility of reaching
these pollutants up to 14.1 Km distance. The data is based on actual
measurements.
3. Total water
requirement will be increased from 3953 m3/day to 6653 m3/day
after expansion. Industrial Wastewater generation will be increased from 2973 m3/day
to 5593 m3/day after expansion.
The treated effluent water characteristics prevailing in
NFCL is submitted and found that all parameters are well within the specified
limits.
The data for Raw Water Inlet and Effluent
outlet ha been rechecked and the Heavy Metals results have been corrected in
Raw Water analysis. Also, the additional parameters of TKN, Cyanide, Ar and V
have been incorporated in the Table 3.4.11 which are as per the CPCB guidelines
for Fertilizer Industry.
Spent catalyst will be sent to
the authorized recycler/reprocessor. Waste oil will be used for lubrication
process. Spent activated carbon generated from the process plants will be
disposed to vendors authorized by APPCB.
The design philosophy followed
for Ammonia/Urea Fertilizer complex is to have ammonia storage tank for safely
consideration in order to take care of plant interruptions of urea plant and to
sustain the continued operation of the ammonia plant. Normally the ammonia plants
are designed with matching capacity of urea plants.
As mentioned at S.N. 6.
in assessing the Tsunami hazard
along each section of coastline, four probability ranges were developed based
on the range of return periods of tsunamis of around 5 m (16 ft) elevation. The
assessed hazard is the general elevation along that coastline and does not
account for localized variation sin tsunami heights caused by seafloor
topography or coastline shape. The four probability ranges have been
demonstrated.
Revised QRA Study was conducted
considering the possible worst case scenario which is catastrophic rupture of
Refrigerated Atmospheric Ammonia Storage Tank leading to Toxic released
scenario of Ammonia into the atmosphere. The study has been done with respect
to new tank of 10000 MT capacity which will be storing a maximum Quantity of
5000 MT of liquid ammonia at any time as per the operating Philosophy of NFCL.
The quantitative risk assessment (QRA) of the ammonia storage facility at NFCL
Kakinada has indicated that the individual risk and societal risk parameters
are in acceptable region.
It was informed that there has
been no major occurrence of near misses in the Complex in the last two to three
years. Further, there have been absolutely no near misses in the area of
Ammonia Storage facility. However, details of near misses in the Complex in the
last two to three years period is submitted.
Ammonia produced in directly
consumed to manufacture urea. As such, during normal and steady state plant
operations when Ammonia and Urea Plant loads are matched, then no ammonia is
sent to ammonia storage tank. But during interruptions of urea plant or lower
load of Urea Plant with respect to ammonia load, liquid ammonia is stored in
the storage tank which is consumed back on restoring normalcy in Urea Plant.
After
detailed deliberations, the Committee noted that risk assessment carried out by
the Unit was found to be satisfactory and suggested to stipulate following
specific conditions alongwith other environmental conditions while considering
for accord of environmental clearance:
i)
All the conditions stipulated in environmental clearance J-11011/31/90-IA (II)
dated 14th October, 1991, J-11011/8/92-IA (II) dated 22nd October, 1992, J-11011/65/96-IA (II) dated 15th
January, 1997 and J-11011/862/2008-IA (II) dated 10th June, 2009
accorded for the existing projects should be satisfactorily implemented.
ii)
The gaseous emissions (SO2, NOx, NH3, HC and Urea dust)
and particulate matter from various process units shall conform to the norms
prescribed by the CPCB/SPCB from time to time. At no time, the emission levels
shall go beyond the prescribed standards. In the event of failure of any
pollution control system adopted by the unit, the respective unit shall not be
restarted until the control measures are rectified to achieve the desired
efficiency. Stack emissions shall be monitored regularly.
iii)
Adequate stack height shall be provided to Ammonia plant reformer, Heat
recovery steam generator (HRSG), NG/ RLNG fired gas turbine and Prilling Tower. Low NOx burners shall be provided
to control NOx emissions.
iv)
In Urea Plant, particulate emissions shall not exceed 50 mg/Nm3.
Monitoring of Prilling Tower shall be carried out as per CPCB guidelines.
v)
Ambient air quality data shall be collected as per NAAQES standards notified by
the Ministry vide G.S.R. No. 826(E) dated 16th September, 2009. The
levels of PM10 (Urea dust), SO2, NOx, Ammonia, Ozone and
HC shall be monitored in the ambient air and displayed at a convenient location
near the main gate of the company and at important public places. The company
shall upload the results of monitored data on its website and shall update the
same periodically. It shall simultaneously be sent to the Regional office of
MOEF, the respective Zonal office of CPCB and the A.P. Pollution Control Board
(MPCB).
vi)
In plant control measures for checking fugitive emissions from all the
vulnerable sources shall be provided. Fugitive emissions shall be controlled by
providing closed storage, closed handling &conveyance of
chemicals/materials, multi cyclone separator and water sprinkling system.
Fugitive emissions in the work zone environment, product, raw materials storage
area etc. shall be regularly monitored. The emissions should conform to the
limits stipulated by the APPCB.
vii)
Additional water requirement from Godavari River for the expansion plant should
not exceed 21170 m3/day and prior permission shall be obtained from
concerned Authority and a copy submitted to the Ministry?s Regional Office at
Bangalore.
viii) As
proposed industrial effluent should not exceed 2620 m3/day and
treated in the ETP. As proposed, Urea plant process condensate shall be treated
in a deep hydrolyser followed by stripping. Ammonia plant process condensate
(APC) shall be stripped with steam followed by activated carbon and
demineralization. Treated condensate shall be recycled/reused in the process.
Utilities wastewater shall be treated in the ETP and treated effluent shall be
recycled/ reused. Treated effluent shall also be monitored for the parameters
namely ammonical nitrogen, Nitrate, Fluoride, pH etc. The treated effluent
which can not be reutilized should be disposed off through marine outfall (MOF)
system. Sewage shall be treated in STP and treated water shall be
recycled/reused within factory premises to achieve zero discharge except rainy
season.
ix)
All the effluents after treatment shall be routed to a properly lined guard
pond for equalization and final control. In the guard pond, automatic
monitoring system for flow, and relevant pollutants (i.e. pH, ammonical
nitrogen, nitrate nitrogen etc) shall be provided with high level alarm system.
x)
The company shall obtain Authorization for collection, storage and disposal of
hazardous waste under the Hazardous Waste (Management, Handling and
Trans-Boundary Movement) Rules, 2008 and amended as on date for management of
Hazardous wastes. Measures shall be taken for fire fighting facilities in case
of emergency.
xi)
Spent catalysts and used oil shall be sold to authorized
recyclers/re-processors only.
xii)
The company shall strictly follow all the recommendations mentioned in the
Charter on Corporate Responsibility for Environmental Protection (CREP).
xiii) The
unit shall make the arrangement for protection of possible fire hazards during
manufacturing process in material handling. Fire fighting system shall be as
per the OISD 117 norms.
xiv) Occupational
health surveillance of the workers should be done on a regular basis and
records maintained as per the Factories Act.
xv) Green
belt shall be developed in 33 % of the plant area. Selection of plant species
shall be as per the CPCB guidelines.
xvi) Remote
operated valve placed on NH3 line to avoid leakage/equipment check
should be performed to ensure that remote operated valve (ROV) is all time is
functional.
No comments:
Post a Comment