GMP Observations in Production
1]
General procedure:
1.1 Quality Assurance
personnel shall make plant round to check adherence of cGMP and fill up the
checklist.
1.2 AMQA/Executive/Designee
shall review the plant audit observation and after compliance/discussion
with plant Incharge audit report shall be closed.
1.3 QA Executive or
Designee shall ensure the compliance of the observations
1.4 There
is no need to have advance intimation or area permissions for plant audit.
1.5
Abnormalities/discrepancies can be complies online by production personnel
1.6 bnormalities/discrepancies
except check list shall be reported and same shall be attached.
1.7
In case of following critical noncompliance observed during plant audit
AMQA/Executive/Designee shall be inform through GMP incidence
report.
a)
Breakdowen of
equipment/instrument during production.
b)
Missing /non
availability of controlled document.
c)
Non availability
of material status label.
1.8
GMP incidence report having ten digit i.e. GIR/XX/YYY.
a.
Where first 3 digits is for GMP –Incidence Report GIR fallowed by slash.
b.
Forth and fifth digit XX represents last two digit of the current year. e.g.
(01, 02…99),with
slash.c. Sixth,
seventh and eight digits (YYY) is sequential no. (001 to 999).
1.9
Filled GMP incidence report along with corrective& preventive action shall
be review and approved by site quality head.
1.10
Incidence of GMP due to any discrepancies shall be reported.
2]
During
plant audit Inspect /Check following points Following Check points
shall be thoroughly considered during plant audit.
2.1
Calibration status of temperature indicators, pressure gauge, online pH meter,
vacuum gauge, flow meters.
2.2
Preventive maintainace records of all manufacturing equipment.
2.3
Weighing balance calibrated and observations are recorded as per SOP; ensure
standard weights are calibrated by authorized laboratory.
2.4
Manufacturing process is strictly fallowed as per controlled BMR and check for
online recording.
2.5
Samples from relevant stage are sent to Q.C.
2.6
Dispensing of Raw Material is done as per BMR for quantity, label status and
ensure material is kept at defined place according to storage condition
.2.7
Calibration status of equipment displayed near the equipment?
2.8
Are the status boards of equipment updated? e.g. ready for use, to be cleaned,
under maintenances, current status of process
2.9
Usage log book for the equipments available and updated on routine
basis2.10 Does a manhole of reactors covered?
2.11
Check the centrifuge bag, filter cloth, Nutch filter cloths stored with proper
identification as per their respective SOP.
3]
Check for House keeping:-
3.1
Review the area cleaning record as per schedule and SOP
3.2
Cleaning and maintenances records of air handling system and filters updated
3.3
Ensure that Floor, Walls, Ceilings and High level surfaces, Light fittings,
window/ doors, AC, Air inlet/outlets properly maintained and cleaned.
3.4
Processing area have restricted entry i.e. Entry exit procedure is followed.
3.5
Ensure that all employee must fallow the gowning procedure.
3.6
Does Standard Operating Procedure are followed and displayed.
Thanks for sharing this article as I felt it very informative. But we also like to inform you about Makpol Industries is one of the India’s leading Centrifuge Bag Manufacturers, who offer a wide range of centrifuge bags. They also offer products like Centrifuge Bags, Filter Pads, ID Fans, Filter Cloth, FBD Bags and many more items. For more details, click on the highlighted words or visit our website.