It is today morning standing meeting at Pinnapuram Site incharge Shri SKB Vali sir enforced to all associates improve quality of activities to monitor daily

 




This daily checklist is designed for the trial/commissioning phase of a 1000 MW solar plant, focusing on verifying equipment functionality, safety compliance, and power generation performance (e.g., during the 30-day trial run). 

1. Safety and Housekeeping (Daily Pre-start)

Safety Gear & Protocol: Verify all personnel are using proper PPE (Hard hats, safety shoes, arc flash protection).

Lock-out/Tag-out (LOTO): Verify LOTO is in place for any maintenance work to prevent accidental energization.

Site Security & Access: Check perimeter fencing and ensure security protocols are active.

Housekeeping: Ensure inverter rooms, substations, and cable trenches are clean and free of combustible materials. 

2. PV Field Array Inspection (Module Maintenance) 

Visual Inspection: Inspect modules for damage (cracks, breakage).

Soiling & Shading: Check for excessive dust, bird droppings, or new shading objects (vegetation growth).

Mounting Structure (MMS): Inspect for loose nuts/bolts and check for corrosion.

Cable Management: Ensure DC cables are not dangling, damaged, or resting on the ground.

Vermin/Bird Control: Remove bird nests or vermin from arrays and junction boxes. 

3. DC System & Combiner Boxes 

Combiner Box (SMB) Inspection: Verify all SMBs are sealed, water-tight, and free of moisture/corrosion.

DC Terminations: Check that all connections are tight to prevent hot spots.

Fuse Holders: Verify all string fuses are properly seated.

Polarity Check: Confirm correct polarity at the inverter input. 

4. Inverter Station (PCU)

Alarm/Warning Check: Review SCADA for active alarms, trips, or derating.

Environmental Check: Confirm cooling fans, filters, and heat sinks are operating properly.

Voltage/Current Check: Monitor DC input and AC output voltage, current, and frequency.

Energy Generation: Record daily active power and compare against expected generation. 

5. AC System, Transformers, & Switchyard

Transformer Condition: Check WTI (Winding Temperature Indicator) and OTI (Oil Temperature Indicator).

Oil Levels & Leakage: Inspect transformer conservator tank (MOG level) and check for oil leakages.

Breakers/Isolators: Verify status of AC breakers and protection relays.

Earthing System: Visually check earthing strips for continuity and proper connections.

Breather Inspection: Check the dehydration breather (Silica Gel) of the transformer. 

6. SCADA, Communication & Weather Station (WMS) 

Data Accuracy: Ensure all inverters, SMBs, and meters are online and sending data.

Sensor Cleaning: Clean irradiance sensor plates and ambient/cell temperature sensors.

Time Synchronization: Verify all devices are synchronized with the central SCADA time.

Performance Evaluation: Monitor for any underperforming zones. 

7. Performance & Reporting (Trial Period Specific)

Performance Ratio (PR): Calculate daily PR (Target >75-80% based on project standards).

Capacity Utilization Factor (CUF): Monitor daily CUF.

Energy Delivered: Log total energy delivered to the grid (kWh/MWh).

Logbook Maintenance: Ensure all faults and maintenance actions are documented in the plant logbook. 

8. Civil & Site Infrastructure

Drainage: Check for blockages in drainage channels to prevent water logging.

Roads: Ensure site roads are accessible and in good condition for vehicular movement.

Street Lights/CCTV: Verify proper operation of per

imeter lighting and surveillance cameras.