Monday, 12 January 2026

Shri SKB Valli sir continously monitoring

 The data and records collected during the first-time acceptance trials and observation of a solar power plant fall into two main categories: documentation review and on-site testing/performance data. This process ensures the plant is installed correctly, operates safely, and meets its design specifications and guaranteed performance levels. 

I. Documentation and Records for First-Time Acceptance

Before any physical testing begins, a comprehensive set of "as-built" documentation must be compiled, reviewed, and approved. 

Project Design Documents:

Detailed technical specifications (GTP) for all major equipment (modules, inverters, transformers, etc.).

Single-line diagrams (SLD) and layout/installation drawings.

"As-built" drawings showing any deviations from the original design.

Design basis report, including expected solar insolation and energy yield simulations (P75 values).

Certifications and Approvals:

Permits and local/state authority approvals (e.g., Chief Electrical Inspector to the Government - CEIG).

Grid connection approval and documentation from the local utility/DISCOM.

Type test certificates for modules (IEC 61215/61730), inverters, and other equipment from accredited labs.

Calibration certificates for all monitoring meters and weather station instruments.

Manuals and Warranties:

Installation, operation, and maintenance (O&M) manuals.

Warranty/guarantee certificates for all equipment, including product and performance warranties.

Health and safety documentation and emergency procedures. 

II. Data Recorded During Commissioning Trials and Observation 

On-site testing and a trial observation period (often 7-15 days for a performance ratio test, or a longer period for annual guarantees) involve collecting specific electrical and performance data. 

Visual and Mechanical Inspection Records:

Checklists confirming proper module mounting, alignment, and structural integrity.

Verification of correct polarity and secure electrical connections.

Confirmation of appropriate labeling and signage for all circuits, disconnects, and safety information.

Electrical Test Data:

Open Circuit Voltage (Voc) measurements for each string/array, compared to expected values (temperature-corrected).

Short Circuit Current (Isc) measurements for each string/array.

Insulation Resistance tests for all DC and AC circuits to check for ground faults.

Continuity tests of protective earthing and bonding conductors.

I-V Curve Tracing data (current vs. voltage characteristics) for a sample of strings to analyze performance, fill factor, and detect defects.

Performance Monitoring Data (via SCADA):

Solar Irradiance (measured in W/m²) using a calibrated pyranometer, logged in the SCADA system.

Ambient and Module Temperature data.

AC and DC power output (kW/MW) and total energy generation (kWh/MWh).

Inverter operational data (voltage, current, frequency, power factor, status logs).

Performance Ratio (PR) calculations, comparing actual output to the theoretical expected output under measured conditions.

Operational Records:

System startup and grid synchronization times.

Logs of any inverter tripping, ground faults, or system malfunctions during the trial run.

Punch lists (snag lists) of minor outstanding defects identified during inspection for the contractor to resolve. 

No comments:

Post a Comment