Before energizing any Underground (UG) cable, two important tests are performed to ensure safety and reliability.


✅ Continuity Test


This test checks whether the cable conductor is properly connected from one end to another without any break.


Process:


✔ Isolate the cable

✔ Short one end of conductor

✔ Check resistance using Multimeter/Ohmmeter


Low resistance means cable continuity is OK.


✅ IR Test (Insulation Resistance Test)


This test checks the insulation health between:


Phase to Phase


Phase to Earth


Process:


✔ Isolate and discharge cable

✔ Connect Megger leads

✔ Apply test voltage

✔ Record IR value in Mega Ohms (MĪ©)


Higher IR value indicates healthy insulation.


Why These Tests Are Important?


✔ Prevent cable failure

✔ Improve system reliability

✔ Detect insulation damage

✔ Ensure safe energization

✔ Important for QA/QC & commissioning