The total project schedule is assumed to be 26 months of which broadly consists of two major activities viz., FEED phase For 8 months followed by the Implementation phase of 18 months. The completion of FEED phase coincides with the FID

 The total project schedule is assumed to be 26 months of which broadly consists of two major activities viz., FEED phase For 8 months followed by the Implementation phase of 18 months. The completion of FEED phase coincides with the FID

(Final Investment Date).

The six (6) months preceding the commencement of FEED will be utilised for the following activities –

i.

Carry out assessment of the borewell capacity (to check suitability for availability of water for 25 years)

ii.

Carry out geotechnical investigation at few critical locations (STG building, Syngas compressor location, storage tank

location), which can be provided to the EPC bidders.

iii.

Carry out Rapid EIA to identify if there are any environmentally sensitive locations nearby that can either become

showstoppers or impact the project schedule/cost.

iv.

Draft PPA (discussions and agreement on key contract and commercial terms)

v.

Commence survey of routing for cross country Ammonia transfer piping from plant to storage location near port

vi.

Identify land near port and commence action to acquire the land parcel; once completed, commence route survey

for piping from storage location to port.

vii.

Commence Pre-FEED and identify Technology Licensor (for the Ammonia plant) and FEED contractor.

viii.

Identify suppliers of other major equipment and long lead items such as Electrolysers, ASU, and Power transformers

ix.

Obtain technical inputs required for submitting application to MOEF.

x.

Preliminary discussions with CTU for obtaining ISTS waiver and discussions with SLDC/STU for connectivityapproval