Development of Solar Parks and Ultra Mega Solar Power Projects
Objective
Solar power projects can be set up anywhere in the country, however the solar power projects developed in scattered manner leads to higher project cost per MW and higher transmission losses. Individual projects of smaller capacity incur significant expenses in site development, drawing separate transmission lines to nearest substation, procuring water and in creation of other necessary infrastructure. It also takes longer time for project developers to acquire land, get all types of clearances and permissions etc. which ultimately delays the project. To overcome these challenges, the scheme for “Development of Solar Parks and Ultra-Mega Solar Power Projects” was rolled out in December, 2014 with an objective to facilitate the solar project developers to set up projects expeditiously.
Period
Up to 2025-26
Salient Features
A solar park is large chunk of land developed with common infrastructure facilities like transmission infrastructure, road, water, drainage, communication network etc. with all statutory clearances. Thus, the solar project developers can set up solar projects hassle-free.
The scheme was rolled out by Ministry of New & Renewable Energy on 12-12-2014. Under the scheme, it was proposed to set up at least 25 Solar Parks and Ultra Mega Solar Power Projects targeting 20,000 MW of solar power installed capacity within a span of 5 years starting from 2014-15.
The capacity of the Scheme was enhanced from 20,000 MW to 40,000 MW on 21-03-2017. These parks are proposed to be set up by 2025-26.
The scheme envisages supporting the States/UTs in setting up solar parks at various locations in the country with a view to create required infrastructure for setting up of solar power projects. The solar parks provide suitable developed land with all clearances, transmission system, water access, road connectivity, communication network, etc. The scheme facilitates and speed up installation of grid connected solar power projects for electricity generation on a large scale.
All the States and Union Territories are eligible for getting benefit under the scheme.
The capacity of the solar parks shall be 500 MW and above. However, smaller parks are also considered where contiguous land may be difficult to acquire in view of difficult terrain and where there is acute shortage of non-agricultural land.
The Solar Parks are developed in collaboration with the State Governments and their agencies, CPSUs, and private entrepreneurs. The implementing agency is termed as Solar Power Park Developer (SPPD). There are 8 modes for selection of SPPDs.
CFA Pattern:
Under the scheme, the Ministry provides Central Financial Assistance (CFA) of up to Rs. 25 lakh per solar park for preparation of Detailed Project Report (DPR). Beside this, CFA of up to Rs. 20.00 lakh per MW or 30% of the project cost, including Grid-connectivity cost, whichever is lower, is also provided on achieving the milestones prescribed in the scheme.
The various modes for selection of SPPD and eligibility of CFA under various modes are given as under: