Planning of Commissioning Activities for Ammonia Plants
The key in the planning of commissioning is the definition of functional systems. Functional systems are sections of the plant, which are put in service as one process system.
Commissioning packages must be defined according to this systemic approach. In case such a detailed planning of activities has never been carried out before in a specific plant, enough resources must be foreseen for the execution of this comprehensive task.
A concise stage 1 plan gives an overall guide to the commission activities to be undertake
A detailed stage 2 commissioning schedule will provide a very accurate duration for all commissioning activities to be performed
The development of a concise and accurate commissioning schedule of activities is very important not only to the overall loading of the project schedule, but the plan also becomes an excellent guide for the commissioning team in the correct prioritization and execution of the various steps that make up the whole commissioning effort.
This level of commissioning schedule must represent the generic range of commissioning activities that the team will perform throughout the project and the time it will take to complete each action
Scheduled activities and timings that must be considered for inclusion within the Phase 1 commissioning scope are:
Agree commissioning scope
Support design at: Hazard Study, P&ID reviews, Layout reviews, 3-D Model reviews
Compile commissioning resource plan
Determine handover philosophy
Determine plant acceptance criteria
Confirm product validation criteria
Compile initial commissioning philosophy
Systemize the plant
Compilation of the commissioning manual
Period for selection and appointment of the commissioning team
Develop detailed commissioning plan
Training period for the commissioning team
Agree operating procedure production requirements by commissioning team
Compile commissioning documentation
Compile training manuals
Compile Operating Procedures
The objective of this level of commissioning schedule will be to accurately determine each individual activity the team will perform and its duration.
As the stage 2 commissioning schedule concentrates on actual delivery of the commissioning activities, it is very detailed in composition.
The stage 2 plan will commence after the mechanical completion milestone date per system. Therefore, this level of detailed commissioning schedule cannot be logically completed (activities can be populated to the schedule), until the construction group has been given a breakdown of commissioning systems and therefore planned their mechanical completion dates according to all the factors which the construction team will need to consider; examples will include delivery of equipment, erecting of steelwork and major pipework systems.
A list of example system activities that must be considered for inclusion in a Stage 2 commissioning schedule are:
Attendance at factory acceptance tests and inspections
Train plant and maintenance operatives
Check construction progress
Test and clean pipe and equipment – per system
“Dry” functional tests (e.g. loop tests, rotating direction tests, cold alignments)
Refractory dry out work requires a specific dry out process to avoid cracks because of evaporating water.
Leak tests (e.g. tubes of heat exchangers) to locate repair scope
Leak tests of manholes prior to catalyst filling or for low pressure systems
Special attention to flange surfaces
Special attention to the gasket(s)
Special attention to the tightening procedure
Blowing, post-work cleaning, packing and internal installation
Catalyst loading
Reduction of catalyst: Most of the catalysts in ammonia plants are delivered in the oxidized form and must be reduced by application of hydrogen. In most cases this commissioning step takes place after most parts of the plant have been commissioned and plant is in startup operation.
Lubricants, oils, cooling media etc. in test plant utilities
Electrical energization and utilities introduction sequentially
Receive discipline approvals
Punchlist – per system
Loop testing – per devise, per system
Motor rotation checks – per item within a system.
Turbine and compressors checks. In many cases commissioning of turbines and compressors requires the availability of high and medium pressure steam. Therefore, these commissioning activities, machine control and interlock tests are performed also during the start-up of the plant.
Leak testing – per system
Drying of functional systems (Check for the quality of drying can be performed by measurement of dew point (recommendation below -20 °C).
Purging of functional systems
Sequence check-out without chemicals
Commissioning on safe chemicals, water commissioning – per system
Utility system start – up
Instrument air system
Cooling water
Nitrogen grid
Steam for heat purposes
Loop tuning within a system
Testing of control sequence s, interlocks and shut-down systems on safe chemicals
Heat tracings and heaters are taken into service.
Burners check: during the commissioning of the burners, control interlock sequences as well as performance parameters, like flame shape and colour are checked.
Lubrication units (joint check plant operator with vendor)
Complete all PSSR paperwork and/ or Hazard Studies 4 and 5 – per system
Issue first draft SOPs
Start-up procedures
Validation period
Acceptance period
Ramp up of production to design rate period
On the job training of operations
Handover to operations
Consolidation period, updating of documentation with best operational
Housekeeping adequate for start-up
Floor and tripping hazards
Scaffolding sufficiently removed / in place for start-up
Delayed jobs under control (working permits, fenced off without interfering with start-up activities, no works during critical stages)
Adequate lighting
General access to buildings and escape routes clearly identified
Access for operations and maintenance
Guarding of machinery
Safety devices in operation (emergency stop devices, emergency showers, sprinklers)
Insulation enough to avoid blockages in the process and critical exposure of people
Sealed surfaces and pits cleaned / emptied to avoid contamination or blockage of sewer systems
Position and tightness of drain valves checked
Safety relieve systems like blow down systems or weep hole systems checked, burst discs in place; all transportation securities are removed
Blinds removed from plant in a controlled and systematic way
Orifice plates correctly mounted
Lock, chains, seals and tags removed from valves
Temporary gauges, valves, fittings and similar dismantled
Caps, plugs and temperature element pockets are correctly fitted and equipped with thread tape
Provisional utility connections and nitrogen hoses removed
Connections to blind flanges removed
Caps mounted
Check interlock override list and shut down panel overrides according start-up procedures
Bypass valves closed. In case of an open bypass valve with “shut off” function the interlock is in “override” mode
Labeling of valves, instruments, lines
All modifications checked against Engineering Lead Documents (e.g. P&IDs, Isometrics)
References:
Killcross, M.: “Chemical and Process Plant Commissioning Handbook” (2012)
De – & Recommissioning Guidelines for Ammonia Plants, Hans Juergen Essl, Leonhard Werner, Borealis Group Austria
Safe Pre-commissioning and Commissioning of a Multi-Product Syngas and Ammonia Facility, Omer Hashmi Selas Linde North America, Nrup Patel Linde Engineering India,
Fernando Rivera Linde Jubail Industrial Gases Factory LLC
Health Safety Executive UK, “HSG 253 – The safe isolation of plant and equipment” (2002)
No comments:
Post a Comment