Crude
Oil
1.
Crude oil production during
April 2016 was 2956.81 TMT which is 0.14% lower than monthly target and 2.27% lower
than the production achieved in April 2015. Unit-wise
and state-wise crude oil production is given at Annexure-I. Unit-wise crude oil
production for the month of April, 2016 vis-à-vis April, 2015 has been shown in
Table-1 and month-wise in Figure-1.
Table 1: Crude Oil Production (TMT)
Oil Company
|
Target
|
April (Month)
|
2016-17 (P) (Apr-Mar)
|
2016-17
|
2015-16
|
% over last year
|
Target
|
Prod.
|
Prod.
|
ONGC
|
22393.40
|
1797.05
|
1801.51
|
1815.35
|
99.24
|
OIL
|
3280.10
|
260.30
|
261.41
|
280.71
|
93.12
|
PSC
Fields
|
10839.32
|
903.59
|
893.90
|
929.34
|
96.19
|
Total
|
36512.83
|
2960.93
|
2956.81
|
3025.40
|
97.73
|
|
|
|
|
|
|
P:
Provisional
Figure-1:
Monthly Crude Oil Production
Unit-wise
production details with reasons for shortfall have been given in following sub-section:
1.1 Crude
oil production by ONGC during April, 2016 was 1801.51 TMT which is 0.25 %
higher than the monthly target but 0.76% less when compared with April 2015.
Reasons for shortfall in production are as under:
·
Offshore: Carrying out reconstruction
activities under ‘Reconstruction of BPA & BPB Platforms’ Project. BPB
shutdown affected condensate receipt at Hazira
·
Mehsana: Less than envisaged production
due to less air injection in Santhal, stoppage of air injection in Lanwa field
due to high H2S, increase in number of sick wells & water cut
·
Assam: Low gas lift pressure in Geleki
field due to non-availability of gas lift compressor
·
Cauvery: Less than envisaged production
from Kamlapuram, & Narimanam fields
1.2
Crude
oil production by OIL during April, 2016 was 261.41 TMT which is 0.43% higher
than monthly target but 6.88% less when compared with April 2015. Reasons for
shortfall in production are as under:
·
Restriction in bowser movement due to
Assam bandh on 18.04.2016, bandh at Tinsukia District on 12.04.2016 and
incessant rain in the operational areas
·
Non-availability of bowsers during
Assembly elections
·
Loss in production from gas lift wells
due to power supply failure
1.3
Crude oil production by Pvt. /JVs during
April 2016 was 893.90 TMT which is 1.07% lower than the monthly target and 3.81%
less when compared with April, 2015. Reasons for shortfall in production are as
under:
·
Panna/Mukta: Less production due to
planned shutdown of SBM from 28.04.2016 to 03.05.2016
·
Cairn: Less production from RJ-ON-90/1
due to closure of 02 High water cut wells. Less production from CB-OS/2 due to
stoppage of gas lift compressor for maintenance
·
GSPC: Underperformance of wells in
KG-OSN-2001/3
·
Natural Decline in Ravva, Mangala &
underperformance of Bhagyam wells in RJ-ON-90/1
·
Under performance of wells of KG D6 due
to sand ingress and water loading
·
Production from M&S Tapti stopped in
March, 2016
Natural
Gas
2
Natural gas production during April 2016
was 2488.07 MMSCM which is 1.33% lower than the target for the month and 6.83% lower
than the production during corresponding period of last year Unit-wise and
state-wise natural gas production is given at Annexure-II. Unit-wise natural
gas production for the month of April, 2016 vis-à-vis April, 2015 has been
shown in Table-2 and month-wise in Figure-2.
Table 2: Natural Gas Production (MMSCM)
Oil Company
|
Target
|
April (Month)
|
2016-17 (P) (Apr-Mar)
|
2016-17
|
2015-16
|
% over last year
|
Target
|
Prod.
|
Prod.
|
ONGC
|
22743.43
|
1621.33
|
1630.95
|
1782.20
|
91.51
|
OIL
|
2905.55
|
236.94
|
250.35
|
194.81
|
128.51
|
PSC
Fields
|
8425.44
|
663.35
|
606.77
|
693.52
|
87.49
|
Total
|
34074.42
|
2521.61
|
2488.07
|
2670.53
|
93.17
|
P:
Provisional
Figure-2:
Monthly Natural Gas Production
Unit-wise
production details with reasons for shortfall have been given in following
sub-section:
2.1 Natural gas production by ONGC during
April, 2016 was 1630.95 MMSCM which is 0.59% higher than the monthly target but
8.49% less when compared with April 2015. Reasons for shortfall in production
are as under:
·
Mumbai High: Reconstruction activities
under “Reconstruction of BPA & BPB Platforms” Project
·
Eastern Offshore: Closure of both the
sub-sea wells of G1 field for carrying out tie-in works for hooking of well
S2AB with G1 facilities
·
Ankleshwar: Decline in production in
major fields of Ankleshwar
·
Tripura: Less off-take by OTPC (one unit
under maintenance), Baramura TSECL & NEEPCO Monarchak
·
Tamil Nadu, Cauvery: Closure of wells
due to less off-take by consumers.
2.2 Natural gas production by OIL during
April, 2016 was 250.35 MMSCM which is 5.66% higher than the monthly target and 28.51%
higher when compared with April 2015.
2.3 Natural gas production by Pvt. /JVs during
April 2016 was 606.77 MMSCM which is 8.53% lower than the monthly target and 12.51%
less when compared with April, 2015.
Reasons for shortfall in production are as under:
·
Underperformance of wells of
KG-OSN-2001/3 (GSPC).
·
Less gas production from CBM-blocks
(ESSAR/RIL/GEECL) due to various issues like dewatering, lack of pipelines and
consumers.
·
Under performance of wells of KG D6 due
to sand ingress and water loading
·
M&S Tapti: Production stopped in
March 2016.
·
Natural Decline in Ravva, PY-1 and
Hazira.
·
Underperformance of wells of
KG-OSN-2001/3
Refinery
Production (in terms of crude oil processed)
3
Refinery production
during April, 2016 was 20155.67 TMT which is 5.16% higher than the target for
the month and 17.95% higher than the production during corresponding period of
last year. Unit-wise crude oil processed for the month of April, 2016 vis-à-vis
April, 2015 has been shown in Table-3 and month-wise in Figure-3.
Table 3: Refinery Production (TMT)
Oil Company
|
Target
|
April (Month)
|
2016-17(P) (Apr-Mar)
|
2016-17
|
2015-16
|
% over last year
|
Target
|
Actual
|
Actual
|
IOCL
|
64299.99
|
5349.77
|
5313.07
|
4052.37
|
131.11
|
BPCL
|
24999.95
|
2065.29
|
2040.84
|
2030.39
|
100.51
|
HPCL
|
16500.42
|
1415.53
|
1517.69
|
1289.98
|
117.65
|
CPCL
|
10250.20
|
907.30
|
875.74
|
939.11
|
93.25
|
NRL
|
2669.99
|
224.17
|
216.53
|
1.46
|
-
|
MRPL
|
15300.00
|
1170.00
|
1165.91
|
1111.42
|
104.90
|
ONGC
|
44.59
|
3.87
|
6.81
|
4.00
|
170.16
|
BORL
|
6000.00
|
525.00
|
533.58
|
1.51
|
-
|
HMEL
|
9000.00
|
770.34
|
920.19
|
895.89
|
102.71
|
RIL
|
69561.01
|
5044.02
|
5846.48
|
5044.02
|
115.91
|
EOL
|
20291.64
|
1690.99
|
1718.85
|
1718.43
|
100.02
|
TOTAL
|
238917.79
|
19166.28
|
20155.67
|
17088.58
|
117.95
|
P: Provisional
Note: Refinery production by NRL and BORL during
April, 2015 was negligible due to planned shutdown
Figure 3: Monthly
Refinery Production (TMT)
3.1
PSU Refineries’ production during April, 2016 was 11136.58 TMT which was almost
at par with the target for the month and 18.11% higher
than the production achieved in the corresponding month of last year. Reasons
for shortfall in production by some of the refineries are as under:
• IOCL,
Paradip: Throughput lower as secondary units are still under commissioning and
stabilization.
• IOCL,
Guwahati & Digboi: Lower crude availability
• BPCL,
Mumbai: Unplanned shutdown of crude unit (CDU3) for maintenance works.
• BPCL,
Kochi: Intermediate
HSD stock built-up due unplanned shutdown of VGO/HDS & DHDS for one day.
• CPCL,
Manali: Throughput in Manali refinery was lower than target to contain VGO, as
Hydrocracker Unit throughput was limited due to high Reactor differential
pressure. Hydro-cracker Unit was under shut down for 10 days since 29.04.2016
for Reactor catalyst scooping.
• MRPL,
Mangalore: Throughput restricted due to water crisis
• NRL,
Numaligarh: lower availability of Assam crude.
3.2 Production
in JV refineries during April, 2016 was 1453.77 TMT which is 12.23% higher than
the target for the month and 62.00% higher than the production achieved in the
corresponding month of last year.
3.3
Production in private refineries during April, 2016 was 7565.32 TMT which is 12.33%
higher than the target for the month and 11.87% higher than the production
achieved in the corresponding month of last year.
3.4 Refinery-wise
details of the capacity utilization and production of petroleum products during
the month of April, 2016 vis-à-vis April, 2015 are given at Annexures-IV and V
respectively.
************
YKB/Rk
hai , is there any job requirements in 2017 please let me know,thanking you www.tseclonlinebillpayment.com
ReplyDelete